Media Update

Welcome to the onsite operations!  We will keep this page updated regularly – please visit often.

Live site capture will be updated frequently!

Construction/Operations Update

1. Construction – 100% complete.

2. Commissioning – 95% complete. Final hot commissioning activities underway from Aug. 2 – Aug. 15 2022.

4. Operations – the facility is fully staffed (13 employees total) to operate the facility 24/7. All employees have had a lengthy period of learning the operation of the facility and we expect to achieve and maintain a steady operational environment.

Our goal is to be operational very soon!

MLTCBE, MLTCII, NorSask, WGL, Mühlböck, and other personnel watch as the first test-batch of lumber is loaded into our new Mühlböck Contunious Kiln.

Our newest MLTC BioEnergy Process Operator. Jim Villbrun, welcome to the team!