Construction/Operations Update
1. Construction – 100% complete.
2. Commissioning – 95% complete. Final hot commissioning activities underway from Aug. 2 – Aug. 15 2022.
4. Operations – the facility is fully staffed (13 employees total) to operate the facility 24/7. All employees have had a lengthy period of learning the operation of the facility and we expect to achieve and maintain a steady operational environment.
Our goal is to be operational very soon!